Production process
* Dryer: It is required to dry bulk materials (sand, fine additives, cement), ensuring sufficient material for the blending mill.
Main equipment: Dosing system must ensure accuracy; The conveyor system of materials must be dry, clean and tight; The drying system is suitable for capacity and economy.
Dryer specifications
* Measuring, measuring, mixing and packing system:
Diagram of the system of blending and bagging.
Note:
1. Feeding system (already quantified components)
2. The hopper contains the material before mixing
3. Mixing device
4. The hopper contains the grinding mixture
5. Tripod
6. Rack bracket
Paint composition by expected weight: Portland Cement (TP1); Quartz sand (TP2); Superfine mineral additives (TP3); Liquid chemical additives (TP4).
Diagram of the system of blending and bagging.
Mixing and grinding process:
Step 1: TP1 + TP3 crushed 60 minutes: to increase the fineness and uniformity of the three components.
Step 2: (TP1 + TP3 (60 minutes crushed)) + TP2 crushed for 8 minutes, mix the fine mixture with aggregate, less time to avoid grinding fine aggregate.
Step 3: Bag the dried ingredients.
No comments:
Write comments